The Street Reporters Newspaper

…Breaking News with Integrity!

Adsense

TCN logo on issues surrounding the inability of the Benin Electricity Distribution Company (BEDC) to supply 20 hours of power supply to its band A customers.
Across States Featured Post Governance News

TCN Reacts To North East Governors on Power Blackout, May 27 Timeline for Power Restoration

Spread the love

The Transmission Company of Nigeria (TCN) has assured the North East Governors Forum (NEGF) that they are doing everything possible within their power to ensure the restoration of power supply to the North Eastern axis of the country, as earlier indicated in TCN’s press release of 10th May, 2024.

In a statement signed by its spokesperson, Ndidi Mbah, the transmission company said “We are acutely aware that the lack of power supply presents significant difficulties and challenges, and we understand the concerns of the governors for their people and the day-to-day running of governance and businesses. We are not happy about the situation.”


Re-emphasising the commitment of the company to to rebuild four towers affected by the activities of vandals, the TCN also assured that their team “has been tirelessly working to rebuild the four towers destroyed by vandals, and we will not rest until power is restored to all the affected areas. We appeal for a little more patience, as work is truly advancing. We are pushing our contractors very hard to ensure we deliver on our promise of rebuilding the towers and energizing the transmission line.

ALSO READ  ALGON Seeks Collaboration with Federal Ministry of Health to Improve Primary Healthcare Delivery

“Despite the recent increase in vandalism, we have continued to rebuild towers each time they are damaged and have consistently restored supply.

“The four vandalized towers on the Gombe axis are no exception. Despite our prevailing poor liquidity, we have mobilized all necessary resources to ensure this job gets the attention it requires.
“To expedite the work, we have insisted that the contractor put in place and on-site machines that will help increase the fabrication processes of tower members which is ongoing.

ALSO READ  NNPC Limited Declares 'War' on Crude Oil Production Challenges in Nigeria

“A visit to the site will show that the towers are nearing completion, with one tower at 90% completion, another at 80%, a third at 60%, and the fourth at 40%.
“We are utilizing all available daylight hours for the work. However, due to security issues, we are unable to work through the night, which we would have gladly done.

“Nevertheless, we are optimistic about completing the reconstruction and energizing the line within the given time frame. We expect power supply to be restored by May 27, 2024, through the new 330kV transmission line, allowing Yola and Jos DisCos to offtake and distribute optimally from TCN substations.
“Again, we appeal for your patience and sincerely assure you that we are working very hard to complete the work within the timeframe.

ALSO READ  Dangote Refinery: Peter Obi Calls for Support, Warns Nigeria of Economic Consequences of Failure

“It is our joy to serve you and the nation at large, and we would be truly happy and grateful to God for the quick completion of the work. Please bear with us”, TCN stated.

StreetReporters.ng

Comrade James Ezema is a veteran journalist and media consultant. He is a political strategist. He can be reached on +2348035823617 via call or WhatsApp.

Discover more from The Street Reporters Newspaper

Subscribe now to keep reading and get access to the full archive.

Continue reading